Scope of Work
This project involved slab-on-grade paving of a trucking yard extension using 1,200 yd3 of reinforced concrete per the client’s request. Croell Ready-Mix recommended FiberForce 750™ at a 5#/yd3 dose to save time and money as compared to steel reinforcement on the slab. Croell’s recommendation proved successful as the client was incredibly happy with the results.
-
Location
Cheyenne, WY
-
Date
August 2022
-
Owner
Old Dominion
-
Area
-
Volume
1,200 yd3
-
Engineer
-
General Contractor
-
Concrete Contractor
-
Ready-Mix Concrete Supplier
Croell Ready-Mix
-